Hi expert,
I have a consignment scenario where there will be batches of shipment at the same period of time.
I have created one PIR for the consignment item, for example:
Material A
Vendor A
From 01.08.2011 to 31.08.2011
Price USD 450.00
Then I performed Consignment GR Batch A. The batch can last for 2 months (Aug and Sept 2011)
At the same time, I have another shipment, for example:
Material A
Vendor A
From 01.09.2011 to 30.09.2011
Price USD 500.00
I performed Consignment GR Batch B. This batch can last for 2 months as well (Sept and Oct 2011)
Under this scenario, if I consume the material during September for Batch A, system will capture USD500.00 instead of USD450.00 which is wrong. How do I track the price validity by batch?
Is there any other approach/workaround pertaining to this scenario?
Thank & regards,
JT