Hello experts
I did already a lot of research and I made also some tests in the SAP system but I didn't find any answer to my question.
I have two work centers. Both should work for Projects and for maintenance orders or orders in general. The capacity planning and the workforce planning for projects (CMP1,3 e 9) is all clear. I have two work centers, assign them to a project and with the transactions mentioned before I can assign a person to the activity for the projects. But now I want to setup the maintenance order in a way that I'm able to make the workforce planning.
I create a new order with IW31. There I'm going to maintain a work center for the first operation. In the operation itself I maintain the work load, the date and the assignment for the person. I release and schedule the order.
Afterwards I'm able to see the requirement for this work center in the CM50.
Now my question
If I want to make the workforce planning report I can't see the assignment of the person I assigned before in the order. I can only see assignments of project activities. How can I handle this issue? Is there a change to be made on the work center or are setup some categories or profiles wrong?
I'm looking forward to get a helpful answer and I'm thanking all of you who are going to reply to this thread
Best regards
Jimsonweet
Edited by: Jimsonweet on Nov 21, 2011 1:23 PM
Edited by: Jimsonweet on Nov 21, 2011 1:24 PM