Hi All,
I have some problem with cost center assignment to profit center.
I have cost center CC1 from period 01.01.2010 to 31.12.999, it has been assigned to Profit center PC1 since 01.01.2010.
But from 01.01.2012, cost center CC1 want to assigned to PC2.
How I can do that?
I already try to change it through tcode OKEON.
First I change the Date and Preview Period as of 01.01.2012, then I change the profit center assignment of cost center CC1, then I save it.
But when I display the CC1 in OKEON and I see tab Organization, the field Profit Center change become '+'. How it can be like that?
And I'd like to know how is the correct way to change the profit center of cost center from certain period, how can I achieve that?
Please advice, thank you.