on 11-18-2011 3:19 PM
Hi All,
We can run Deployment with and w/o SNP Check horizon
Please tell me what would be the difference
1. Running TLB after Deployment which has been run w/o SNP Check horizon
2. Running TLB after Deplyment which has been run using SNP check horizon
I am asking this specifically as the TLB has been generating orders reduntantly and I am wondering if this issueis becasue of not using SNP check hor
SS
Hi,
The SNP checking horizon controls the ATD issue calculation.
If you specify an SNP checking horizon, deployment calculates the ATD quantity for a period within the SNP checking horizon by adding the ATD receipts for the current period and the past periods and subtracting all ATD issues within the SNP checking horizon.
For example if you maintained SNP checking horizon is 5 days , the sales order lies on the sixth day will not be considered for calculation of ATD issue.
Thanks and regards
Thamizh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thamizh,
Thanks so much for the prompt response.
Can you kinldy let me know what would the impact of this be on the subsequent TLB run.
In my case, there was a TLB order created initailly for date xx:yy:2011 basing on the available supply / stock .
The next day , when deployment and subsequent TLB ran, the result was another TLB order with shipping date one day prior to xx:yy:2011.
So now two TLB orders are existing for the same materials / quantities but diferent dates ie First TLB order with shipping date on wednesday and the second one with shipping date on Tuesday
Can anyone kindly explain this and also let me know if this can be solved by using SNP check horizon
Regards,
SS