Skip to Content
0
Former Member
Nov 18, 2011 at 01:59 PM

IW70 Scheduling Calendar different than the PM Capacity scheduling Calendar

235 Views

If I scheduling work orders using IW32 or IW38 SAP uses the maintenance calendar selected in the capacity of each work center, set for 365 days 24 hours. When I schedule using IW70 SAP selects the factory calendar that includes holiday/weekends that are non work days. Is there a way to config. IW70 to use the maintenance calendar?