on 11-17-2011 2:26 PM
Hi,
I'm testing if the central Contracts are displayed automatically when creating a PO (ME21N). The contract has been created in SRM. In ECC the contract is saved in table CC_DB_VIEW.
Is it possible that the contract is automatically assigned to the PO, when entering the vendor and material. For PIR this works fine.
Regards,
Alexander
The document type for Central Contracts was not linked to the NB document type of the PR and the PO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The document type for Central Contracts was not linked to the NB document type of the PR and the PO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The document type for Central Contracts was not linked to the NB document type of the PR and the PO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Create Contract Release Order Thru ME25.
Follow the steps from this document:
http://help.sap.com/saphelp_470/helpdata/en/75/ee0f4d55c811d189900000e8322d00/content.htm
Reetesh
Edited by: Reetesh Tiwary on Nov 17, 2011 3:52 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.