We have below situations,

There are 4 products which are shared by same resource & relevant to SNP.

Bucket : Weekly

Resource should not be utilized less than 50 % in any bucket, if total demand of all the product is greater than 50% of capacity requirement than only it should create plan orders.

I have gone through 100% resource utilization blog in SCN but my requirement is reverse of that so was not able to relate.

I cant use minimum lot size in PPM as there are multiple products are using same resource.

How can we restrict resource to use minimum % or quantity level ( minimum qty to produce ).

Let me know if you understood my concern properly.

Regards,