on 11-16-2011 5:00 PM
Dear Experts,
When doing Refurbishment subcontracting from IW81 everything was going ok and when goods issuing the material to be refurbished it appeared in MMBE in stock provided to vendor but the problem is when going goods receipt from MIGO with MVT TYPE 101 it gives an error that the equipment status ESTO does not allow goods receipt, this doesnot happen in normal subcontracting maintenance order, i dont think the problem is in the equipment status ESTO as itis normal to be ESTO during subcontracting any ideas?
Thanks in Advance
Dear Mr Serry,
r u using split valuation for refurbishment process. If it is check the valuation type are PMREF.
regards
Rajendran R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can also try using t-code ADSUBCON for the subcontracting goods movements.
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Before doing MIGO we need to run IW8W .Hope then problem would be resolved.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.