on 11-16-2011 12:19 PM
Hi All,
When the cost estimate is created (CK11n), the cost component (facility) calculated the cost incorrectly.
Activity (Lead Time) - 18.6 Weeks
Planned Activity/Cost center value - 1,000 (Fixed Value)
Work Center Formula calculated = 18,600 (Correct)
But the cost estimate (Cost component - Facility) calculates amount = 19,000 (Incorrect)
Looks like the lead time 18.6 is rounded to 19 weeks in the cost estimate calculation. Can somebody assist in getting the actual amount 18,600 in the cost estimate?
Thanks,
Thameem
Hi
See if Note 380796 - Rounding error in the cost estimate is relevant.
Regards
Eduardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.