on 11-16-2011 9:25 AM
Dear Team,
We are creating a Debit Memo Request from DP91 for a resource related billing. The reference SD document for DP91 is a contract.
The Sales unit in this case is 'HR - Hours" . But when the Debit memo is created , pricing picks up another unit of measurement i.e. H- Hour. Hence my price conversion in condition screen looks like this :
"EK01" = 100 H.... 3600 HR = 3600 H.
(This specifically happens for EK01 condition type.)
Kindly help in resolving this issue. Also pls let me know in case any further info required.
Regards,
Kanwar
Hi Kanwar,
Please check UOM for the activity in your network (CN22) and activity master KL02.
Regards,
P Gomatheeswaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kanwar,
First of please let me know your process, prior to DP91, is it in "PS", on a normal services scinario.
You pls check the condition record in "KP26" where, the actitvity type and unit should be mentioned properly.
then try again.
Also You sholud maintain DIP Profile for Resource rel;ated billing.
DIP Pfofile use "ODP1" and its consitency check use "ODP2A".
regards
DSR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I understand your process is like service processing with a service contract.
Here you raise a service order were you maintain your Unit at the bottom of header screen of service order (IW31), in "Oprtn Duration" along with time.
I hope you have maintained controll Key "sm02/sm03"
then try ref. to the service order >Serviice confirmation (IW41)> DP90> DMR > Billing (RRB).
It sould work out
here It has nothing to do with pricing.
I hope my solution is relevent to your context, if not pls revert back.
regards
DSR
Edited by: D.Srinivasa Rao on Nov 16, 2011 12:50 PM
Hi,
While running DP90 / DP91 system calculates the costs as per the records maintained in KP26.
This is happening because in KP26 the unit of measure is maintained as H=Hour. You can maintain UOM as H in material master also so that in Debit Memo Request, it will be H only.
Hope this helps.
Regards,
Sharan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sharan,
In KP26 the correct UOM is "HR" maintained and which is the required UOM. Also in CUNI we have maintianed ISO units corresponding to HR.
UOM "H" is not the desired UOM for any document processing, but still it is cropping up and shows up in pricing with the conversion factor as mentioined above.
Regards,
Kanwardeep