Regarding configuration of "Parameters for determining the basic dates"

Hi All,

Can anyone give inputs in which scenario we need to use the configuration "Parameters for determining the basic dates".

1)Do we have any restrictions for usage of above IMG configuration, 2) any pre-requisites to use the configuration of "Parameters for determining the basic dates" and 3)does configuration of this task is having any integration with any other modules, if yes what is the point of integration with other modules.

Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Nov 16, 2011 at 06:50 AM

    Dear

    1. Use T-code OPU3 there u find all the Adjust Dates and so on

    2. Use T-code OPKP

    3. And Schedule Margin Key In Master Data there U find Define Floats

    With Regards

    Pushpalas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 16, 2011 at 08:34 AM

    Dear Aditya,

    Parameters for determining the basic dates in production order are used to calculate the Basic Start date & End date of Production order. It Determines if and how the basic dates or the dependent requirements dates are adjusted during lead time scheduling. You can customize this in OPU3 for planned order & OPU5 for Production Order.

    There are the following possibilities:

    1.The basic dates are adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.

    2.The basic dates are not adjusted and the dependent requirements are scheduled for the start dates of the relevant operations.

    3.The basic dates are adjusted and the dependent requirements are scheduled for the order basic start date.

    4.The basic dates are not adjusted and the dependent requirements are scheduled for the order basic start date.

    1)Do we have any restrictions for usage of above IMG configuration

    For scheduling this has to be. If you want that start date should be calculated based on Inhouse production time & not on routing select opetion 2 or 4

    2) any pre-requisites to use the configuration of "Parameters for determining the basic dates"

    Not as such

    3)does configuration of this task is having any integration with any other modules

    Not directly but with MM to determine dependent requirement Proposal.

    Regards

    ABhijit Gautam.

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Abhijit,

      Thanks a lot for ur immediate reply.

      This thread is closed and points are awarded for all who gave valuable suggestions like you.

      I have some other threads in forum regarding Print Control(OPK8) and Splitting Forecast Requirements of MRP configuration which are open now.

      Please provide your inputs for my other Queries(Threads) in the forum when you are free.

      Thanks Again. Take Care.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.