cancel
Showing results for 
Search instead for 
Did you mean: 

Infotype 0019 Monitoring of Task

Former Member
0 Kudos

Dear All,

When Im trying to create Infotype 0019 system is not defaulting date in the field Date of Task. Client is complaining that earlier date used to appear in that field automatically.

I too understand that we have to give the date there manually. but client is insisting that earlier it used to be default.

Also as per the below link it is been given that date will defaulted. Can anybody tell me if there is some entries missing in any of the tables.

http://help.sap.com/saphelp_46c/helpdata/en/7e/5e04d34a1611d1894c0000e829fbbd/content.htm

Thanks

Ravi..

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Closed..done ABAP coding for defaulting Date of task from DOJ..

Former Member
0 Kudos

Use Dynamic action but to my knowledge date of hire will automatically default in IT0041 that we did through Dynamic action.

Best Regards,

Former Member
0 Kudos

Friends,

Please refer to the above URL. In that it is clearly mentioned that date can be defaulted.

Thanks

Ravi...

Former Member
0 Kudos

The link what u said is to default the dead line of the task based on the back end configuration but I am not sure of the Hire date.

Best Regards

Former Member
0 Kudos

In the URL it is mentioned that hiring date can be defaulted, but nowhere it is mentioend how it can be done..

any inputs plz..

Former Member
0 Kudos

Hi,

"The system suggests a default date independently of the task type. This date can be overwritten at any time"

As given in the link for reminder date.

Reminder date is the date used to remind about the task type configured with the task date.The following configuration is to be carried out, i.e. PA->Evaluation Basis->Monitoring of Task->Determine task type. The reminder date is the date which reminds about the task u will need to perform.

There are 3 options to remind according to the configurations done, one is same as the task date, other is date before task date and the final one is date after task date. Selecting this will automatically create the required reminder date as per config.

If no time unit for follow up/lead time is given in the config part for your task type system automatically takes the task type date as the required reminder date.

Think it is clear now.

regards.

Edited by: Vishnu AG on Nov 11, 2011 2:11 PM

Edited by: Vishnu AG on Nov 11, 2011 2:18 PM

Former Member
0 Kudos

Hi,

Date in 0019 wont be defaulted on its own. It is done through Dynamic actions. Check dynamic actions for defaulting 0019, when a person is hired, or promoted.

regards.

Former Member
0 Kudos

Hi,

Use dynamic actions for the same.

Thanks & Regards, Swapnil