200 Views

We are implementing a new plant for our Singapore operations that is assigned to a new company code with a different currency. We need to convert open production order master data to the new plant. I tried to create new ones using CO01 with reference to the old order. I get a warning message that the production and planning plant are different. The order then gets created with the old plant. Is there a method to create these easily in the new plant? I am an FICO person doing PP work, so a bit of a novice here. Any help is appreciated.