on 11-09-2011 9:32 AM
Dear Experts,
I am able to create CU order from CU Design , However I am not able to capture Cost in the CU order.
I have assigned a TL and assigned couple of operations with some labor hours.
May be I have missed some thing !
Can any one suggest @ cost capturing in CU order ?
Regards,
Rahul
Hi,
Welcome to sap.sdn.forum.
I think you sould consult your FICO/COPA people to take care of costing so that you can maintain cost elements and activity assignment in "KP26" for hourly billing for labour hours (also use work centre for labour).
regards
DSR
Edited by: D.Srinivasa Rao on Nov 9, 2011 10:54 AM