Hi,
When I am trying to display the PIR material in MD63, MD73 I'm getting the below error saying,
" No requirements were found which correspond to the selection criteria "
Bt we are getting some dependent requirements in MD04 whereas i couldn't display it in MD63.
Pl help me to get this..
With Regards + Thanks ,
Paveetra
MD 63 displays planned independent requirements and not dependent requirements created thru planning run. you can see that in MD04,cick on the lens for detailed view
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You cannot view dependent requirements using MD63/MD73 which is for Planned independent requirements.
The dependent requirements include dependent reservations and stock transfer requirements.
I.e if the material you are planning has got the components in BOM , system will consider that also.
If you dont want this you can set the MRP dependent indicator as 1 in the Material master - MRP 4 view.
Thanks & Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.