Hi,
I have three plants viz. 1000, 2000 and 3000.
Finished product F1. Its BoM has Semifinished SF1, semifinished SF2 . And SF1 and SF2 have few ROHs also.
Finished Product F2. Its Bom has SF3 and SF4. SF3 and SF4 have few ROHs also.
Finished Product F3. Its Bom has SF5 and SF6. SF5 and SF6 have few ROHs also.
Its MTO scenario.F1, F2, SF1, SF2, SF3,SF4, SF5 and SF6 are extended to all three plants as required. Through Procurement key and special procurement type we define which all are inhouse production or procured from other plants through Stock transport Purchase orders.
First case: Cient may create sales order for F1 in plant 1000. System will create planned order for production order of SF1 and STO for SF2 to plant 2000.
Second case : Directly sales order may be created for SF1 in plant 1000 also.
Similarly sales order can be created for F2 or F3 or SF1 or SF2 or SF3 or SF4 etc in different plants.So currently I run MRP in MD01 for plant 1000, then I run for Plant 2000 and then for 3000.Then I run again in plant 1000 to generate requirements in 1000 plant .But actually I want to run MRP at plant level in background.
What should be my setting ? shall I run in background for plant 1000 then 2000 then 3000 or shall I run for all three plants at a time, if yes then how??
Kindly guide.
Regards.