Dear SDN,
please, is there any user exit that runs whenever a WBS is saved, even if there was no change at the WBS level?
I need to check the WBS Project Type against its sub-Activity Cost Element (the WBS can contain more than 1 Activity), whenever the button SAVE is pressed.
Any kind of help is highly appreciated.
Regards,
Fabio
Hi,
Maybe you can use EXIT_SAPLCOBT_001. It has old and new value in the exit parameter.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Fabio,
Please check with BADI PROJECTDEF_UPDATE,BADI WORKBREAKDOWN_UPDATE.
Regards,
Madhu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Madhu,
thanks a lot.
It does work, however still not exactly as I need, as it doesn't get triggered when a Network Activity under the WBS is changed. Only when the WBS itself is changed.
I think I will have to find another BADI for the Activity, and exchange the info via SAP memory.
What do you think?
Thanks a lot.