on 11-04-2011 1:28 PM
Dear gurus,
i need planned the materials in the periodic modality, are there the type MRP in the material master for create the planned file ( table MDVM) one once a month or in the specific period chose ?
Example :
I need that the material master don't create a file planned ( MD20- TABLE MDVM) for a change of the requirement situation new , but i would like that the flag in the table ( MDVM) or file of the planning MRP created when the today date is in the period specific.
31.3.2011 (or period 1.4.2011- 10-4-2011)Date for the create a file MRP and after when run MRP planned the material, for others scenary the system must not planned the material.
Are there the MRP type for my problem? Or the customizing setting?
Thanks a lot
Dani
Dani,
Not sure if MRP type or customizing can help here. And even if we are able to achieve this requirement it will be applicable at plant level.
However, try exploring option of periodic lot size (weekly, monthly, etc). This will work according to period you've set and should give you the results you are looking for.
Regards,
Himanshu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.