on 11-04-2011 10:54 AM
Resource Category 0008 is not showing any set up time in the scheduling tab ?
am I missing a config settings ?
Dear
Please Check What Type Of Standard Value Key Ur taking Under that Standard Value key ur taking
Suppose ur taking SAP1 --- then u get Setup time Machine time Labour Time
SAP4 then u get Duration so in order to get the values for ur Selection u need to Customize in SPRO
Use T-code OP19 there u can give your Values According ur requirement
With Regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I assume you are asking capacity category in Scheduling tab. Please check customization CRC1.
Regards
Abhijit Gautam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.