Skip to Content
0
Former Member
Nov 03, 2011 at 02:06 PM

Material Reservations and PO

258 Views

Hello,

my question is at which stage of the network the material (components) reservations or Purchase orders, automatically trigger.

when the project (with networks and materials) is created or released.

because I have issue like the project is in TECO and for some reason we are planning to undo the TECO. if I undo the status, will it again creates the PO or reservation.

Is there any document, which explains in detail about the configuration of PS -MM integration.

Is there any concept like labor reservation just like material reservation. I am not sure is question itself true or not.

Thank You