on 11-03-2011 6:08 AM
Dear Gurus,
I have a scenario, we have project systems PS. We have valuated projects and valuated project stock. Once project is over and if we have material left over, then my client want to charge the cost of the material to the project but he want to keep the stock at zero value in inventory, and issues it next time on zero value.
I have tried to transfer material using 415 Q, but system does not allow to transfer materaial from valuated project to non-valuated project.
kindly suggest any solution.
Hi,
To change the valuated project stock to non valuated project stock The Non-valuated project stock indicator must be set in the project definition. In the material master, the Individual/Collective indicator on the MRP 4 tab page must be set to Individual (1) or Individual/Collective (). Please refer below link for better clarity. Thanking you.
http://help.sap.com/saphelp_45b/helpdata/en/4c/227be846e611d189470000e829fbbd/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
my client wants to charge the leftover material cost to project but want to keep the qty in stock, so this is why we have a nonvalauted project. otherwise my client projects are valuated. i have not find any solution to charge the cost of material to project from project stock and keep the stock in inventory on zero value. and next time when this leftover is issued it will be issued on zero value.
hope u have a solution.
Edited by: Johi Kapoor on Nov 10, 2011 11:57 AM
Hi,
You can transfer valuated project stock to non valuated project stock using the movement type 309 Q in MB1B transaction. Thanking you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You have already costed this material in the project and hence there is no question of transfering stock to same project at 0 cost.
Also, once project is over you will not be required to keep stock in that project. You customer must be asking to keep stock at 0 value in inventory only so that for any future project it can be issued directly.
Regards,
Dakshesh
User | Count |
---|---|