Planning time fence MRP and MPS

Dec 20, 2016 at 01:54 PM

69

avatar image

Hi , i need help regarding the freezing period issue . In business we are using one material master in a plant with 21 days of planning time fence.

We created the plant calendar and we added in Friday it means in the opening days are from monday to friday with 6 opening days a week

After the MPS processing ( planning type = M1 '' MPS, fixing type 1 '' ) . In MD04, the system calculated the planning time fence.in function of the current opening days ( Monday to friday which are 5 opening days a week ).

In MD41, for the same material, the system calculated the freezing period based on the opening days of plant calendar ( 6 opening days a week ).


We are confused because for the same material we have to different freezing periods which are bad for the business. I need help to understand and excute the best solution

Regards

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

RAJASEKAHARA REDDY BANNURU Feb 16, 2017 at 02:32 AM
0

Hi
Could you please clarify your below mentioned Point : Monday to Firday ( 6 Days) ?


Thanks & Regards : Raja Sekhara Reddy B