Hi , i need help regarding the freezing period issue . In business we are using one material master in a plant with 21 days of planning time fence.
We created the plant calendar and we added in Friday it means in the opening days are from monday to friday with 6 opening days a week
After the MPS processing ( planning type = M1 '' MPS, fixing type 1 '' ) . In MD04, the system calculated the planning time fence.in function of the current opening days ( Monday to friday which are 5 opening days a week ).
In MD41, for the same material, the system calculated the freezing period based on the opening days of plant calendar ( 6 opening days a week ).
We are confused because for the same material we have to different freezing periods which are bad for the business. I need help to understand and excute the best solution
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.