Hi Expert,

My client needs to do the mass change in Task List Operation description, I tried T code CWBQM, but its shows only QM task list.

Can you guide me any method other than LSMW or BAPI.

Regards

Sandeep Yewle

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Dec 20, 2016 at 03:08 PM

    There is an FM "EAM_TASKLIST_CHANGE" (Check documentation on this FM, which provides a few samples).

    PS : There is a Customer Improvement pending for this, so hopefully something will be provided in the future => D9870

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 29, 2016 at 02:52 PM

    Thanks Nic...