Hi Experts,

We are changing our customizing to activate the document flow update for Inbound Deliveries using Inventory Management transactions.

My question is related to the Inbound Deliveries that are already completed but the Document Flow was not updated, as the Goods Receipt was posted with MIGO transaction and not with VL32N.

Is it possible to update the Document Flow for these Inbound Deliveries?

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

No it is not possible, at least I have never seen a note which provided a report for such purpose

Answers (1)

Answers (1)

Former Member
0 Kudos

Thank you very much for your response Jürgen.