Dear Experts,

Suppose i have an production order of 1000 qty. and i have delivered 900 qty. so now when i take MRP run i don't need this order to be displayed there.

Kindly provide some information.

Regards,

Pankaj

Accepted Solutions (1)

Accepted Solutions (1)

sundaresan_velayudam
Active Contributor
0 Kudos

IF you don't want to process the production order further, Then Better set the Status TECO to production order by selection function --> restrict processing set Technically complete

afterwards system won't consider the production order during MRP

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Flag the final delivery checkbox during MB31 or MIGO - GR posting

Former Member
0 Kudos

Dear Sarkar,

Thanks for the information, but if automatic GR is there then what to do.

Regards,

Pankaj

Former Member
0 Kudos

Hi Pankaj,

There is a checkbox "completed" in goods movement screen at confirmation posting which can be flagged to post GR as final delivery.