on 10-20-2011 1:58 PM
in PDS the '01' resource mode is on proirity 'A' but in the product heuristic run system is selecting the Mode 02 that is with the priority 'B'. system should assign the resorce '01' as its on higher priority.
solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you check in strategy profile what is the setting defined for " Lowest mode priority".
Regards,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Nandkumar!!!
in the global settings for interactive planning, strtegy profile is SAP002 and in Strategy P. SAP 002 the Lowest Mode Priority is blank
is this a information you are asking?
if this is the reason then please help me in this area and elaborate the impact of this setting.
thanks in advance
The mode priority feature was designed to be more of a way to restrict the modes which can be used in an operation than a way of prioritization.
The mode selection itself is made in LiveCache during order scheduling. LiveCache sorts the possible modes according to the availability dates and only after that according to mode priorities
When the "Lowest Mode Priority" setting is not defined in the strategy profile, the system selects for the operation the mode with higher priority when the operation:
ends as early as possible at the forward scheduling
starts as late as possible at the backward scheduling
HI,
If finite scheduling is activated in your profile, and if the resource 01 is already loaded or doesn't have enough capacity to fulfill the order on time, then the heuristic will schedule the order on the resource 02 - the second priority which has enough capacity. So please check the what is the net available capacity of the resource 01.
Regards,
Manimaran M.
hi,
I checked in the resource uttilisation report (/sapapo/cdps_rept) and found that the resorse 01 with mode priority 'A' is 13% utillised lots of free capacity is also available for Res ''01. and the resource 02 which is with mode piority 'B' is 89 % utillised.
for 'A' higher utillisation should be there.
In Addition we did recently SNP go-live, earlier there was only PPDS.