I have a problem using MRP...
The production area of my customer works from Monday to Saturday (calendar1)
The Purchase office works from Monday to Friday (calendar2)
I need to create MRP scenario based on production calendar1 and purchase calendar2.
Does it exist a workaround to use two different calendars in MRP, one for production and one for purchasing?
I need to create MRP forecast, where production orders can have DocDate from Monday to Saturday and purchase orders with DocDate from Monday to Friday.
Regards