Hi gurus,

We have this scenario: We set tolerances for purchasing PP in SPRO, and we do subsequent debit for difference price in MIRO. If this quantity added to invoice is bigger than tolerance, system not allow register it. Ok.

But, we want set different tolerance by material. We want materials with tolerance bigger than others. In SPRO, you can configure tolerances by Vendor. It's an option too but, unafortunately I can't modify quantity to item level, only to header level. We need modify price in item level to modify price average material with the difference. In header not modify this price.

There are more options???