Hi

In COPA in KEPC i have assigned aganist each plant wise and each material type wise.

but when we are doing inter company sales form one company code to another company code

material type is ROH it is throwing error during billing when i removed these material type against that plant

it is allowing me in generating billing douctmetns.

my dout is if i removed raw material , packing material assignment in kepc if i keep only semi finished and finished product would be there any problem in future during billing.

thanks

kareem

Accepted Solutions (1)

Accepted Solutions (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi

thats the right way of doing it.... You shold not have ROH or Pkg Mats in KEPC