Skip to Content
0
Former Member
Oct 20, 2011 at 08:26 AM

Dependent Requirements not being passed for ROH material (After MRP run)

87 Views

I have three materials A, B & C, whose BOM structure is as follows

Material A - FERT (planning strategy 59 i.e. planning at phantom assembly level)

Material B - HALB (planning strategy 70 i.e. planning at assembly level)

Material C - ROH (No planning strategy)

Where, material B is component of A and C is component of B

After maintaining PIRs for material A, ran MRP in MD02, dependent requirements

are being generated for material B but not to material C.

In reference to dependent reqts not being passed on to ROH material C,verified following

1. MRP 4 view --> MRP Dependent requirements is Blank for HALB material B

2. Item details of mateiral C in BOM has right settings

3. X Plant status in Basic Data --> Blank