Assigned cost is greater than the planned cost for WBS element (In CJ33)

former_member306740
Participant
0 Kudos

Dear All,

The issue is Assigned cost is greater than the planned cost for WBS element..

In IW38 for the particular month (say October) the total actual cost is 12,30,891.55.

In CJ33 for that WBS element the details (October month)are as follows.

Release amount:22,92,000

Current budget: 22,92,000

Distributable: 22,92,000

Assigned: 22,85,119

Planned total version : 22,81,276

So now the client wants cost of IW38 (ie 12,30,891.55) should come in the assigned value of CJ33.because assigned is more than the planned so he cannot do further assignment for the remaining orders in the current month.

Kindly guide me in this regard.

Regards,

santosh.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

Dear All,

>

> The issue is Assigned cost is greater than the planned cost for WBS element..

> In IW38 for the particular month (say October) the total actual cost is 12,30,891.55.

> Assigned: 22,85,119

> So now the client wants cost of IW38 (ie 12,30,891.55) should come in the assigned value of CJ33.because assigned is more than the planned so he cannot do further assignment for the remaining orders in the current month.

>.

Assigned = Actual + Commitments + Rem.Order Plan + Fund Reservation.

Please check all the four and compare.

former_member306740
Participant
0 Kudos

In which t-code i can check that one..

former_member230675
Active Contributor
0 Kudos

there are many reports available...

and also you could refer SAP help ..

******

For example report : S_ALR_87013558

Former Member
0 Kudos

In CJ33 itself, click on Extras --> Availability Control --> Analysis

Here you will get the breakdown of the assigned values generated by each object and the business transaction which generated it.

former_member306740
Participant
0 Kudos

Dear all,

if i add both actual cost and Rem order plan iam getting the assigned value.

but now the question is client wants cost of IW38 (ie 12,30,891.55) should come in the assigned value of CJ33.because assigned is more than the planned so he cannot do further assignment for the remaining orders in the current month.

By the way what is rem order plan how cani make it available.

Regards,

santosh.

former_member306740
Participant
0 Kudos

Dear all,

kindly tell me where can i get the detail of Rem. Order Plan.

Regards,

santosh.

former_member230675
Active Contributor
0 Kudos

Rem. Order Plan is temporarily calculated during the execution of project, you can see it in the Structure CCSS under Value Type 25.

Rem. order plan consist of planned labour / work, reservations or planned material components at network level / order level.

Please search the forum for further details as it has been discussed in details earlier..

former_member306740
Participant
0 Kudos

dear all,

can anybody explain me in detail about this.

Regards,

santosh.

former_member230675
Active Contributor
0 Kudos

dear all,

> can anybody explain me in detail about this.

>

> Regards,

> santosh.

Please respect forum rules

*********

Please search the forum, lot of threads available

Former Member
0 Kudos

Dear Santosh,

Budget has been maintained and released at WBS level. When you talk about IW38, I assume that cost has been incurred at maintenance order level which has not been checked for budget. This i believe is standard functionality. The budget at WBS will be checked if you try to settle the cost of the maintenance order to the relevant WBS.

Please check and confirm.

Regards,

Ammar