on 10-19-2011 10:35 AM
How to track operation wise costing during confirmation. i.e, how to findout the cost involved related to raw material , labour,overhead costs etc for each operation wise.
Check the costing report S_ALR_87013127
for Ind Order Check KKBC_ORD
Edited by: Abhijit Gautam on Oct 19, 2011 3:37 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.