Oct 19, 2011 at 05:40 AM

Dispatch Instructions for Direct Supply from Vendor to Customer.

811 Views

Dear Experts,

Our Company is Project Industry. We have implmented SAP ECC 6.0 in 2008 with SD, FI, MM, PP, QM, PS, DMS modules.

In our case 70% Deliveries to customer are from direct dispatch from our vendor to Client. Steps are as follows.

1. Buyer issues PO to vendor for direct dispatch to customer. After readiness of material vendor gives Inspection call to Buyer.

2. Buyer creates inspection notification using T-code QM01.

3. Quality department visit the vendors place, inspect the material & clears the inspection notification.

4. After acceptance of material, Project Execution issues Dispatch instructions to vendor with PO No. & Item details. This is Outside SAP in MS word.

5. Vendor Supplies the material to Customer based on dispatch instructions.l

6. After receipt of dispatch document from vendor, Buyer creates Goods Receipt w.r.t. Purchase order in MIGO. We have Put ABAP check for GR creation to check Accepted Quantity of Inspection notification of that PO line item.

Now our Management wants to Implement above Step No. 4 of creation of dispatch instructions in SAP. At the time of creation dispatch instructions, system shall check if inspection notification is created & allow the creation for accepted PO line item quantity in the notification & only after the inspection notification is closed in SAP . Dispatch instructions should have information such as PO No., Line item no., Material Code, Material Description & quantity to be dispatch, Vendor Name, Project Name.

As per my knowledge in Standard SAP Dispatch Instructions Process is not there.

Request you to give your valuable opinion.