It is used to do sales order availability check..if i go by considering rep lead time, then any order that is after rep lead time will be confirmed because system now has time to procure/produce the material..

but when i enter total rep lead time in material master for in house produced item as 10 days.. then that means to make 1 pc, it takes 10 days for me..

so if i get an sales order for 10 pc, then it takes 100 days for me to produce 10 pcs and satisy the sales order.

If I use check using rep lead time, system will say you can confirm the order by the end of the rep lead time for 10 pc, which is wrong. in reality it takes 100 days from the day i confirm the order to completely produce the order.