Skip to Content
0
Former Member
Oct 18, 2011 at 11:52 AM

Maintenance Plan

9 Views

I have created a multiple counter plan with OR link. The cycle is 250 KM or 500 days with respective counters. My purpose is that, the order should be generated when the measurement reading of 250 KM is entered against that counter. The annual estimate is 1500.So based on last measurement reading done against the counter, the order is getting generated on 18.12.2011.I have created a measurement document of 250 kM on 18.10.2011.Why the order is not getting generated on 18.10.2011 as this is what I want i.e. the order should be generated when the reading is reached.. Am I wrong some where? Pls. advice.