Hi Gurus,
please suggest a possible solutions for this scenario, we process the payment for this vendor with 50% down payment thru F-47 and how to call-up in MIRO with remaining balance only? because when we do the MIRO it reflect the whole price of PO.
Regards,
Marina
Hi:
Deselect the material line items equivalent to the 50 percent amount in MIRO ...Material Tab..Now you will be able to post partial amount as desired.
Regards