Hi,
You can follow the below link for initial learning purpose :http://help.sap.com/saphelp_46c/helpdata/en/fe/67f9609d6f11d189b60000e829fbbd/frameset.htm
You can try the above cycles in IDES Version ..
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Suggest to read some document or SAP Help for detailed information , however the main component of Basic cycle of PM is as below which is used for Breakdown Maintenance ---
1. Problem Identification -
Notification creation
2. Material & Manpower requirement -
Maintenance Order Creation
3. Requirement of spares form Stores -
Reservation creation ( Thro Order)
4. External Service -
PR for external service if required can be created thro Order
5. Start of Work - Release of Order
5. Work completion -
Confirmation ( IW42 / CATS)
6. Service Entry in case of external service
7. Order TECO
8. Settlement of Order to the settlement receiver ( Usually cost center)
9. Order CLSD
Regards
Sameer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.