Dear experts,
How can I identify which production orders' planned costs are calculated or not. I aim to not to make any material movements for this production order without cost calculation.
Dear
In IMG we can define that when we calcu. the planned cost.
There are 3 ways.
- Determine planned costs when saving,
- Do not determine planned costs when saving,
- Determine planned costs when saving if released.
But the actual cost is posted when we draw the material, when we confirm the order......We can use co02 and click the calcu. cost to update the cost in the prd order.
Check the log file in the Production Order -> Goto -> Logs -> For costing
in Coo02 Production order Change Mode Goto>>>>> Cost >>>>> Itemization
With Regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
In IMG we can define that when we calcu. the planned cost.
There are 3 ways.
- Determine planned costs when saving,
- Do not determine planned costs when saving,
- Determine planned costs when saving if released.
But the actual cost is posted when we draw the material, when we confirm the order......We can use co02 and click the calcu. cost to update the cost in the prd order.
Check the log file in the Production Order -> Goto -> Logs -> For costing
in Coo02 Production order Change Mode Goto>>>>> Cost >>>>> Itemization
With Regards
Pushpalas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Filter Order with Status PRC in COOIS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.