Hi All,

After loading the master data DTP, the request becomes greeen but the "Update Master Data Attributes" step is still yellow. Let me know how to overocome this error

Thanks,

Sathya

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

hi,check the data at the point it remains in yellow,so if all records are transferred then it's fine so do like this

1 if all records are transferred ,and still it remains in yellow ,you can change the qm status to green(this is if qm status is also yellow )

2 if all the records are transferred and qm status is green but one of that particular dtp step is yellow ,no problem,you can refresh several times and activate the master data,it will not show any error OK

hope you got it.

assign points if helpful

Former Member
0 Kudos

Hi,

This is a master data full load and it updates more than 1 lakh records. Technically the Overall and technical status of my DTP request becomes Green but when i go to the details tab and drill down the data package the "Update Master Data Attributes" still remains yellow so i dont think my load will update the attributes for my info object successfully.

Is there a solution to overcome or did anyone face this similar issue?

Thanks

Sathya

Former Member
0 Kudos

Hi ,

Do anyone have solution for this ?

Update Master Data Attributes step in DTP is yellow though the overall status of the DTP shoes as completed

Thanks

Sathya

Former Member
0 Kudos

Hi

Check the job log of your DTP in SM37 and make sure it is progressing.

Check you have enough back ground job in SM50.

Regards,

Venkatesh

Former Member
0 Kudos

Hi All,

Here the situation is the job is getting finished and the DTP request also becomes green. But when you actually go to the request details and expand the data package the "Update Master data Attributes" step in Updating attributes for InfoObject still remains yellow.

Have your suggestion on this..

Thanks

Sathya

Former Member
0 Kudos

This situation occur when there zero records updated. thats why it's showing Yellow status under Detail tab. But technicaly your loading is completed that's why overall result shows in Green status.

Regards,

Sushant

+919820849482

Former Member
0 Kudos

check available processes in SM51 to complete this job if the servers are not overloaded.

former_member182470
Active Contributor
0 Kudos

Hi,

Yellow means not an error. Check your DTP job status. Also check the error stack for errors. If everything seems to be OK then you may make it to green manually.

Regards,