on 10-04-2011 7:11 PM
Hi,
In the production order component overview screen, While assigning the batch system shows both assigned and non assigned batches.
Requirement: Once I assign the batch in the production order, it should not display in the list.
What settings in config. i need to do?
Regards / US
Dear
Please Check In COB1 and in MSC1N or MSC2N u can Make batch Selection according to the Classification and After Doing this When u do the Production Order Click on the Components Overview At that Movement Please Click on the Batch Determination then it will Segregates the Batches accordingly
if u there is stock exists u cant remove batch in MSC2N by putting all the delete checks on. There was just one batch created for the material.
With Regards
Pushpalas
Edited by: pushpalas on Oct 5, 2011 9:26 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.