Hi QM gurus

When test scheduling is created for stability study,

inspection lot is auto generate on due date of test schedule or it will create manually

through action box

Regards

AAdi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

inspection lot is auto generate on due date of test schedule or it will create manually

through action box

Mostly it is created through schedule in background by IP30.

Former Member
0 Kudos

means we have to go IP30 after test schedule every time ?

Regards

AAdi

Former Member
0 Kudos

There seems to be some confusion ....

Refer the threads ...Hope you will understand it better ways