Maintenance Plan

Former Member
0 Kudos

If we tick on the completion requirement indicator,and my 1st planned date is 01/01/2011 and next is 08/01/2011

but my 1st order is completed on 09/01/2011,does this mean that my second order due on 08/01/2011 will not be generated?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Completion requirement:

Untill you confirm your previous call object, system will not generate next call object automatically. Anyhow, you can create manual call object.

Based on shift factor for late completion & tolerance, system will create the next call object.

Replica of the scenario:

I have created maintenance plan (single cycle plan) with cycle 10 days & start date as 01.09.2011 with completion requirement.

It has created the order as 11.09.2011 for the first order. I did TECO on 03.10.2011 with the completion date 03.10.2011. Next call object has been created for 21.09.2011.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

MY SAP is not working, but yes this is how it behaves, until u complete the previous call object , u cannot release the next call object