on 10-02-2011 6:41 AM
If we tick on the completion requirement indicator,and my 1st planned date is 01/01/2011 and next is 08/01/2011
but my 1st order is completed on 09/01/2011,does this mean that my second order due on 08/01/2011 will not be generated?
Completion requirement:
Untill you confirm your previous call object, system will not generate next call object automatically. Anyhow, you can create manual call object.
Based on shift factor for late completion & tolerance, system will create the next call object.
Replica of the scenario:
I have created maintenance plan (single cycle plan) with cycle 10 days & start date as 01.09.2011 with completion requirement.
It has created the order as 11.09.2011 for the first order. I did TECO on 03.10.2011 with the completion date 03.10.2011. Next call object has been created for 21.09.2011.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
MY SAP is not working, but yes this is how it behaves, until u complete the previous call object , u cannot release the next call object
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.