Dear QM diamonds

can any body guide me what is prerequisities for repitative manufacturing how to lot creation what the steps need for config or master data ..

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • avatar image
    Former Member
    Oct 01, 2011 at 06:40 AM

    Dear,

    In Rem you have to assigned 13 inspection type in material master with task list check.

    you have to assign MIC in CA22 i.e rate routing and do the setting for inspection points in routing itself for ex. if you want to multiple check hourly etc in operation overview.For that you have to create inspection lot by MFPR and record result and make Usage decision.

    Regards

    Rambabu

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 01, 2011 at 01:35 PM

    Refer very good steps...

    Repetitive Manufacturing - Make to Stock

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 06, 2011 at 03:44 AM

    Hi,

    Master Data -

    Material master creation using T-code MM01

    BOM creation using T-code CS01

    Rate Routing creation using T-code CA21

    Rem profile - SPRO ->Production planning -> Rem.Manuf-

    Assign the REM profile to a material - MRP4 view in MM02

    create Valid Production version - MRP4 view in material master & Check Rem mfg ind

    Assign the BOM and routings in Prod. Version & check the settings.

    Create Product cost collector

    Create material cost estimate

    Create standard cost estimate

    Create planned order for the material and carry out rem process using MFBF

    Now for the raw material ,if u have semi finished material for semi finished material and for finished material assign the inspection type,inspection characteristics and carry out the regular process like results recording and usage decision

    Regards,

    Raj

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 08, 2011 at 06:29 AM

    step1: material master(mm02) go to quality management :click on inspection setup bok: do the entry as per your required inspection :example

    typeMaintain Inspection Type in Quality Management View.

    --Type 1. for GR from Procurement

    --Type 13. for inprocess repetitive manufacturing.

    --Type 3. for GR from Production.

    2. qs32 : create master inspection characteristics

    3. Maintain an inspection plan (T code:QP01) & assign characteistics in it.

    4.Go to T Code: QA32.Choose the icon change inspection lot.There in you can assign inspection plan to the material.Press the sample size button. Then the inspection lot status will get converted to Release.

    i hope it will solve your issue

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 08, 2011 at 06:30 AM

    not qs32 ,it is qs21

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 31, 2011 at 01:11 PM

    Thanks for input

    Add comment
    10|10000 characters needed characters exceeded