output calculation (on the basis of running hour and quantity)

Former Member
0 Kudos

Dear Guru,

scenario:

we have 6 work center and activity type cost will be calculated on basis of output quantity.

ex : work center 1:activity cost: Rs 100

output :100 nos(quantity)

total cost : 100*100= 10,000

like this we are calculating the cost of every workecnter

required sceario :we want to calculate 4 workcenter cost on basis of output quantity and two on the basis of running hour

please help me where we do the changes .

thanks in advance for your suggestion

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Not sure if I understood your query, but based on what little I understand you would need to use a formula which has only duration as parameter & not operation quantity.

Eg: Refer to standard value key - SAP4, which has SAPC00 as a parameter.

Using this you can multiply the cost with the hours irrespective of the operation output.

Do a test in your sandbox & if it meets your need adopt in PRD.

Former Member
0 Kudos

Vivek

THANKS FOR SUGGESTION, IT'S WORKING

Answers (1)

Answers (1)

vasudevap_pushpalas
Active Contributor
0 Kudos

Dear

Are you maintaining the same standard value key for all the work center if it is like that then u have to maintain a a standard value key EX: SAP1 for that Set up,Labor Machine time should be the multiple of Work centers At the End of Costing please check

With Regards

Pushpalas