Replenishment lead time for external procurement/MRP

former_member214692
Participant
0 Kudos

I have a material on an SA and OMI8 is flagged to get the PDT from the Scheduling Agreement or info record. Yet when I run MRP and check the Replenishment Lead Time in MD04, it is clearly pulling the PDT from the material master. How can I get RLT to pull the PDT from the SA or info record? (On the material master, we are using the PDT field to represent something entirely different .... the manufacturing time for the vendor to make the material).

Thanks, Vlad

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Soruce list validity period should be with in the Material requirement date.

Meaning when system is generating the requirements, you should have a valid soruce list inorder to consider the RLT from info record or a Scheduling Agreement.

Thanks,

Satya.

Edited by: satyanarayana ramisetty on Sep 30, 2011 11:56 AM

mauro_bianchi
Active Contributor
0 Kudos

Hi Vlad,

Please check the following:

1.The source list entry is valid during the planning period.

2.The PDT is correctly maintained in the schedule agreement.

Regards,

Mauro