Dear Expert's

Could you let me know what is the process to Override Cost Center for Specific wage types in HR system.

If possible please give me the table name.

regards

Chandra

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I found solution.

Former Member
0 Kudos

Share the solution!

Former Member
0 Kudos

You cannot override cost center for a wagetype as such directly.

If you have specific employee, the you can use "maintain cost assignment" button or control +f2 in IT15/IT14/IT2010 via PA30.

Else if it you want to use one alternate cost center for this wagetype used for any employees, then you can try to explore the possibility of enhancing exit -PCPO0001. You may have to create custom function,as the standard function does not meet your requirement.

The simplest way is to use PA30 updates.

former_member193210
Active Contributor
0 Kudos

For what kind of WT do you want to override the Cost Centre ?

In IT0014 and IT0015, you can override the Fund/Order/CostCentre/FinancialCentre using the "Maintain cost assignment icon (or Ctrl + F2).

Using IT0027 or IT1018, you can override the CC for most expenditures (or employer costs), but not by WT.