on 09-28-2011 5:47 AM
Hi,
I am trying to understand what this transaction does and i am confused what to enter under resource structure values and productive time?
basically can some one please help me understand how to run this t-code to see how my scheduling/prod time determination is calculated.
Thx
dear friend,
CR04 is Test Work Center Formulas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Swati,
This Tcode is used to test the work center formula for scheduling & capacity which you had define in Work center.
Enter Plant & WC for which you want to test you formula.
Enter Operation Qty for which you want to test it say 1000,
Enter base Qty say 1
In standard value keys Enter time required as per base Qty 1
Say Set up time 1Hr
Machine time 1 Hr
Then Click on Scheduling or Capacity Req.
System will calculate the No. of Hr required to produce 1000 qt.
I hope now it is clear to you.
Regards
Abhijit G
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.