Estimation method of progress Analysis

89 Views

Hi,

We are having following scenario.

We are creating the project in PS. Then creating the PM order & assigning

the order to WBS element.

We want to use the Estimation method of progress analysis. Hence we havedefined Estimation method as default measurement method (both plan &

actual )for following objects,

1. WBS element

2. Internal processed activity

3. External processed activity

4. General cost activity

5. Order (Other than Network)

For WBS element & all activities we are able to manually maintain planned

POC & actual POC in CJ20n.

But for PM order we are not able to manually maintain planned POC &

Actual POC.

Can you please let me know where we can manually maintain the planned &

actual POC for PM Order.

regards,

Pradip Shelke