Hi guys,

My PP/DS planning horizon has deifned for 24 hours time period. If sales order comes today, it will be planned tomorrow. If I need to run planning manually of particular sales order same day, when it comes. How should I do?

If the answer is to run product heuristic, Can anyone tell me how product heuristic should be run (the right steps)?

Thanks