Where to maintain planning related / process related minimum interval

Former Member
0 Kudos

Dear Sir,

To have buffer / leeway in planning , SAP has provided the provision for maintaing of the following information :

Planning related minimum interval

Planning related minimum offset

Process related minimum Interval

We do not know where this information can be maintained in the SAP System .

We request SAP experts to kindly guide us about maintaining of the above information into the SAP system .

With Thanks and Regards

Sonia agarwal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Sonia,

These terms are used within APO Detailed Scheduling (part of PP/DS) module. They can be found in certain master data (PPMs and PDS's) and they are used in various scheduling tasks: heuristics, DS planning board, optimizer.

Online help about production order time intervals in scheduling can be found at

http://help.sap.com/saphelp_scm70/helpdata/EN/5f/e9693728e52456e10000009b38f889/frameset.htm

and related pages.

It is quite a daunting task to maintain data that meets a set of business requirements unless you have extensive knowledge of PP/DS. Since you have never done this before, I strongly recommend that you engage an experienced PP/DS resource to assist you in this area. You can spend weeks and weeks using trial and error methods in varying the many interrelated parameters that will have an impact on scheduling. Then, when the client asks you to 'tweak' the results, more weeks.

If you feel compelled to attempt this on your own anyway, then I also suggest that you will get more answers if you post such questions in one of the SCM/APO forums. I suggest that you first read the above mentioned help, including all the subordinate pages and the contained links, before you ask more detailed questions.

Best Regards & Good Luck,

DB49

Answers (3)

Answers (3)

Former Member
0 Kudos

a)maintain in mrp2 view : schedule margine key(float before and after producation)

b) workcenter : 1)capacity header( maintain interval), scheduling mai

actcap requirement: setup,process, tear down,

2)scheduling : queue time

hope it will solved your problem

madlercm
Active Contributor
0 Kudos

I'm not sure what are these parameters that you mention, but for creating planning buffers in MRP planning, you can use the scheduling margin key, where you can maintain predefined slacks - float before and after production.

former_member311826
Active Contributor
0 Kudos

Hi You can use Inter operation field of Work Scheduling view or else in Routing, Go to Operations details try using Inter operations times like Minimum & maximum wait time

Regards

Abhijit Gautam